Home Tender Details


TENDER FOR REFURBISHING OF FLAT NO.41 AT JOLLY MAKER APARTMENT NO.III, CUFFE PARADE, COLABA, MUMBAI 400 005

 

 

 

Notes For Architect / Contractor:

i

Architect / Contractor should inspect site before submitting quote to assess nature/quantum of work, site conditions etc on 19th July 2012 between 2.00 p.m. to 5.00 p.m. with prior appointment with Mr A M Shaikh, Mobile – 9869045506 or Mrs S S Dighe, Mobile 9930970928

 

 

ii

Contractor should adhere to specific timing of work as instructed by Architect/Client, to ensure undisturbed functioning. Contractor is supposed to work late hours as directed to complete the work within stipulated time frame without any extra cost.

 

iii

Contractor will be asked to provide barrication, screen or temp. partitions where ever required to keep working area isolated. Contractor will not be paid separately for the same. This is to maintain other areas in safe, hygienic and undisturbed condition.

 

iv

Best house keeping is the prime requirement of this work and contractor should keep work place in neat and clean condition at any given time.

 

v

Contractor will appoint a competent site engineer who should be in a position to take complete charge of the site and decisions as and when required to avoid time over run.

 

 

vi

During demolition work Contractor should stack and hand over all serviceable material as directed by Architect / Client. All other unserviceable material and debris to be shifted immediately away from site , as directed and dispose it at appropriate places without claiming any extra cost. Contractor should reinstate demolished surface in neat cement plaster in correct line and level without any extra cost.

vii

All veener finishes are to be finished with melamine polish if not specified.

 

viii

 

Contractor should inform architect / client about any extra work (Extra work mean - work which is not covered in this BOQ) before executing it. Any extra work done directly by contractor without intimating Architect and client both will not be paid by client.

 

ix

 

Architect / Contractor should complete the work within four months from the date of commencing of the work

 

x

 

Sealed Tenders may be submitted to Mrs S S Dighe, APO (Admin), AFC India Limited., Dhanraj Mahal, First Floor, C S M Marg, Mumbai 400 001 on or before

25th July 2012.


 

Sr.No

Description

Total Quantity

Unit

Unit Rate

Amount

Remark

 

 

 

 

 

 

 

A

DEMOLITION

 

1

Removal of the existing floor tiles till the slab level

 

1050.00

 

Sq.ft

 

 

 

 

2

Removal of the existing dado tiles, existing water proofing, etc with existing windows of the toilets

 

330.00

 

Sq.ft

 

 

 

3

Removal of the existing windows

195.00

Sq.ft

 

 

 

4

Removal of existing doors with door frames

10.00

nos

 

 

 

 

5

Removal of existing wardrobe in master

Bedroom

 

120.00

 

Sq.ft

 

 

 

6

Removal of the Loft from the store area

15.00

Sq.ft

 

 

 

 

 

Total of Demoltion

 

 

 

 

 

B

285

 

1

 

Floor tile 2'0"x2'0" Vitrified tiles

 

1395.00

 

Sq.ft

 

 

cost of tile only, this may vary as per selection

 

2

 

Laying of Floor tiles and skirting

 

1120.00

 

Sq.ft

 

 

 

 

3

Fixing of floor tiles with Adhesive in the store area

 

70.00

 

Sq.ft

 

 

 

 

4

Providing zari's to electrical contarctor and finishing it with 12 MM plaster with wire mesh wherever required.

 

500.00

 

R.ft

 

 

 

 

5

 

POP Punning on the wall surface

 

2790.00

 

Sq.ft

 

 

 

 

6

 

False ceiling as per Architect's Design

 

975.00

 

Sq.ft

 

 

 

Living, Dining and all bedrooms considered

 

7

 

Colouring

 

3730.00

 

Sq.ft

 

 

plastic paint to be considered

8

Textured Paint Royale impression

275.00

Sq.ft

 

 

 

 

9

Window framing in split level in green marble and white marble

 

320.00

 

R.ft

 

 

 

10

Aluminium window with anodized coating

220.00

sft

 

 

 

 

 

 

 

11

Complete toilet with fixing of dado tiles upto

7'0", window treatment with green marble, Al window, exhaust fan, waterproofing, fibre door for the duct, bund wall, glass door as instructed by the Architect with complete plumbing, simpolo, hindware or similar make European Pan WC, etc. complete: Size

5'0"x10'3"

 

 

 

 

LS

 

 

 

 

 

Basic cost of wall tile

35/-. Existing accessories to be used

 

 

 

12

Complete toilet with fixing of dado tiles upto

7'0", window treatment with green Marble, Al window, exhaust fan, waterproofing, complete plumbing, simpolo, hindware or similar make European Pan WC, etc. Size

5'0"x6'0"

 

 

 

LS

 

 

 

 

Basic cost of wall tile

35/-. Existing accessories to be used

13

AC Drain

4.00

nos

 

 

 

14

Debris transportation

2.00

nos

 

 

 

15

Site Cleaning

LS

 

 

 

 

Total of civil work

 

 


C

Fabrication

 

1

P & F Entrance door safety grill as per architect's design and approval (1'-0" X 4'-0")

 

1.00

 

No

 

 

 

 

2

Safety grill, box type for the window in the

Living area as instructed by the architect.

 

98.00

 

Sq.ft

 

 

 

 

Total of fabrication

 

 

D

Carpentary Work

a

Entrance area

 

 

1

P & F entrance door with TW Frame and finished with veneer & melamine polish as per architectural design.

 

1.00

 

nos

 

 

 

 

Basic cost of veneer - 75/-

 

2

P & F entrance safety door as per design, door to be finished with veneer & melamine polish as per instruction of Architect.

 

1.00

 

No

 

 

 

3

 

P&F wall panelling as per design from

Architect for the entrance lobby

 

36.00

 

Sq.ft

 

 

 

 

 

4

P & F shoe rack cabinet made up of approved plywood & finished with laminate externaly. Cabinate to be finished with 1.5

MM thk. white laminate internaly.            (5'-

0" X 2'-6")

 

 

12.50

 

 

Sq.ft

 

 

 

b

Living room

 

 

 

1

P & F T.V unit paneling as per architectural design with laminate. Size 6'x6' with  4 nos glass panels and 3nos drawers 15" deep.

 

 

36.00

 

 

Sq.ft

 

 

 

 

 

2

 

P & F door with TW frame near the living unit with Laminate as per architectural design.

 

 

1.00

 

 

nos

 

 

 

3

P & F Panelling to cover the AC piping

22.00

Sq.ft

 

 

 

c

Dining Area

 

 

 

1

P & F cutlery unit as per architectural design

& details. Size 2'0" X 6'-0" X 1'-3" . To be finished with laminate of same colour from inside and outside and shutters with wooden frame and glass

 

 

12.00

 

 

Sq.ft

 

 

 

2

P & F Panelling to cover the AC piping

22.00

Sq.ft

 

 

 

 

3

P & F niches (12"x2'0") as approved by

Architect

 

5.00

 

nos

 

 

 

d

Kitchen

 

 

 

 

 

 

1

Replacing the existing shutters with the new laminate of approved shade from the Architect

 

95.00

 

Sq.ft

 

 

 

 

2

P & F 12mm Glass shelves (2'0" wide) at specified location from the Architect with appropriate support

 

2.00

 

nos

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


d

Master Bed room

 

 

1

P & F entrance door with TW frame with

Laminate as per architectural design.

 

1.00

 

No

 

 

 

 

2

P & F entrance fibre door to the toilet with

Green Marble frame in split level

 

z

 

nos

 

 

 

 

 

 

 

 

3

P & F wardrobe (4'-0" X 9'-0" X 2'-0" - 3

Nos) as per architectural design with drawer and shelf inside. Wardrobe to finish with approved 1.5mm thick laminate externally and 1.5 mm thick white laminate inside. Cost includes  all necessay hardware cost

(drawer chanels, SS hooks). Maximum no of drawers to be provided in one wardrobe is 2

Nos

 

 

 

 

 

110.00

 

 

 

 

 

Sq.ft

 

 

 

 

 

 

 

4

 

P & F storage type Bed (6'-0" X 6'-6") as per architectural design with drawer and top pull on one side. Bed to finish with approved

1.5mm thick laminate externally and 1.5 mm thick white laminate inside. Cost includes  all necessay hardware cost (drawer chanels, SS hooks, hinges). Maximum no of drawers to be provided on side is 2 nos.

 

 

 

 

1.00

 

 

 

 

nos

 

 

 

5

P & F Mirror fixed with studs 2'6"x5'0"

12.50

Sq.ft

 

 

 

 

6

P & F TV Panelling with 2nos drawers of 12" deep

 

28.00

 

Sq.ft

 

 

 

7

P & F Panelling to cover the AC piping

22.00

Sq.ft

 

 

 

e

Son's bedroom

 

1

P & F entrance door with frame with

Laminate as per architectural design.

1.00

No

 

 

 

2

P & F 3'-0" X 2'-0"side storage near the

window

6.00

Sq.ft

 

 

 

 

3

P & F entrance fibre door to the toilet with

Green Marble frame in split level

 

1.00

 

nos

 

 

4

P & F TV Panelling

24.00

Sq.ft

 

 

5

P & F Panelling to cover the AC piping

22.00

Sq.ft

 

 

 

6

Replacing the Laminate of the bed and side storage with the approved laminate

LS

 

 

f

Guest bedroom

 

 

1

P & F entrance door with Laminate as per architectural design. Existing frame to be retained.

 

1.00

 

No

 

 

 

 

2

P & F entrance fibre door to the toilet with

Green Marble frame in split level

 

1.00

 

nos

 

 

 

 

 

 

 

3

 

P & F storage type Bed (5'-0" X 6'-6") as per architectural design with drawer and top pull on one side. Bed to finish with approved

1.5mm thick laminate externally and 1.5 mm thick white laminate inside. Cost includes  all necessay hardware cost (drawer chanels, SS hooks, hinges). Maximum no of drawers to be provided on side is 2 nos.

 

 

 

 

1.00

 

 

 

 

nos

 

 

 


 

 

 

 

4

P & F wardrobe (3'-0" X 9'-0" X 2'-0" - 2

Nos) as per architectural design with drawer and shelf inside. Wardrobe to finish with approved 1.5mm thick laminate externally and 1.5 mm thick white laminate inside. Cost includes  all necessay hardware cost

(drawer chanels, SS hooks). Maximum no of drawers to be provided in one wardrobe is 2

Nos

 

 

 

 

54.00

 

 

 

 

Sq.ft

 

 

 

5

P & F Mirror fixed with studs 2'6"x5'0"

12.50

Sq.ft

 

 

6

P & F TV Panelling

15.00

Sq.ft

 

 

7

P & F Panelling to cover the AC piping

22.00

Sq.ft

 

 

 

8

P & F Curtain rods in all rooms at the windows of approved colour

 

50.00

 

rft

 

 

Total of carpentary work

 

 

E

Electrical Work

1

Light point

80.00

nos

 

 

 

2

5 AMP points

25.00

nos

 

 

 

3

15 AMP power points

8.00

nos

 

 

 

4

A/C point

4.00

nos

 

 

 

5

Music system wiring - Living Only

0.00

Sq.ft

 

 

 

6

Telephone wiring

350.00

rft

 

 

 

7

Bell wire

75.00

rft

 

 

 

8

Ele. Circuit

LS

 

 

9

Ele. Fixture cost

LS

 

 

 

 

 

 

 

 

 

 

Total of Electrical work

 

 

 

 

F

Bought out items

1

Sofa seating with 3+2+1 arrangement

1.00

No

 

 

 

 

 

To be decided with client

2

Sofa side tables

2.00

No

 

 

3

Center table

1.00

No

 

 

5

Curtains in all rooms

 

 

 

 

6

Artistic paintings

10.00

No

 

 

7

Artefacts

L.S.

 

 

Total of bought out items

 

 

 

 

 

 

 

 

 

 

 

Grand Total (A+B+C+D+E+F)

 

 

 

 

Contingencies @ 3%

 

 

 

 

 

 

 

 

 

 

 

Net cost of construction

 

 

 

 

 

 

 

 

 

 

 

TOTAL